Example Diagram 1

The above diagram shows the completed project planning of the contract works cost (PCW) of 100 mio over the project time of 36 months. The works are planned according to an engineering, procurement & construction / tests sequence (EPC). 

The planning of the contract scope may comprise about 50 to 60 tasks for the contract works, cost and time, about 40 to 50 spare tasks for the addition works (claims) which may occur during contract execution.

The time schedule levels are

    • Level 0: the entire project (summary / roll up of level 1 tasks),
    • Level 1: the subprojects (summary / roll up of level 2 tasks) and
    • Level 2: the contract works related tasks and if added later, also addition works related tasks (planned tasks)

Link to Example Diagram 2