The above diagrams show the following selected groups related to claims 3 to 7 whereby claims 1 & 2 are not selected , as their previous additional works were transferred into contract works in form of an contract amendment and subsequent re-baselining at project months 20/21:
-
- Diagram 9: Monthly executed additional works (EAW, EPC structured) for the claims 3-7, rolled-up Level 1
- Diagram 10: Monthly executed additional engineering works for the claims 3-7, tasks Level 2
- Diagram 11: Monthly executed additional procurement works for the claims 3-7, tasks Level 2
- Diagram 12: Monthly executed additional consruction works for the claims 3-7, tasks Level 2
The tables at the digrams bottom show the project changes cost magnitude related to their occurrence during the project execution time. The magnitudes for the changes cost from 1-fold at project start up to 6-fold towards project end are based on international experiences .
Link to GTC Home