The above diagram shows
-
- the baseline curve of 100 mio according to the planned contract works (PCW)
- and the re-baselined curve according to the revised planned contract works (PCW) of 114,9 mio in months 20/21.
Link to Example Diagram 3
The above diagram shows
Link to Example Diagram 3